PLANNING THE NEEDS FOR LOADING, EXCAVING AND TRANSPORTING EQUIPMENT FOR OVERBURDEN REMOVAL AT BUANA PIT PT TIMAH INVESTASI MINERAL

Authors

  • Nurwahyu Ramadani
  • Firdaus Firdaus Halu Oleo University
  • Muhammad Ilham Kadar Halu Oleo University
  • WD Rizky Awaliah Nafiu Halu Oleo University

Keywords:

Overburden removal, Excavation equipment, hauling equipment, queuing theory

Abstract

The nickel ore potential in Southeast Sulawesi Province has encouraged PT. Timah Investasi Mineral to engage in mining activities within a Mining Business Permit (IUP) ± 297 hectares, located in Rahampuu Village, West Kabaena District, Bombana Regency, Southeast Sulawesi Province. PT. Timah Investasi Mineral is currently planning to conduct mining operations in a new pit, namely Pit Buana, which covers an area of around 2 hectares with an estimated overburden volume of 74,000 tons. To optimize these operations, a detailed plan for the necessary excavation and hauling equipment is required for the overburden removal process. This study aims to determine the quantity and types of excavation and hauling equipment needed for overburden stripping activities. Based on the results of the study, the number of mechanical equipment used varies at each stage of the operation. For the overburden digging activity, one unit of Komatsu PC210 excavator is used, with an estimated work duration of 33 days. Meanwhile, the overburden loading activity is carried out using one unit of Komatsu PC200 excavator, with a working time of 34 days. For the hauling phase, eight units of Hino FM 260 JD ID dump trucks are employed to ensure the smooth transportation of overburden material.

References

Komatsu. 2019.

Y. Indonesianto, Pemindahan Tanah Mekanis. Yogyakarta: CV Awan Poetih, 2013.

Rostiyanti, Alat Berat Untuk Proyek Konstruksi. 2008.

“Caterpillar Performance Handbook Edition 31 ®,” 1979.

W. , S. Bargawa, Perencanaan Tambang Edisi Kedelapan. Yogyakarta: Kilau Book, 2018.

A. Putri, D. Hidayati, I. Satria Permana, and M. Oktavia, “OPTIMASI ALAT GALI MUAT DAN ALAT ANGKUT MENGGUNAKAN METODE TEORI ANTRIAN DAN KAPASITAS PRODUKSI PADA KEGIATAN COAL GETTING DI PT NATURAL ARTHA RESOURCE.” [Online]. Available: http://ojs.umb-bungo.ac.id/

S. G. Erecelebi and A. Bascetin, “Optimization of shovel-truck system for surface mining Figure 1-Phases of shovel-truck system,” vol. 109, 2009.

Published

2025-06-18

Most read articles by the same author(s)

1 2 > >>