PERENCANAAN BIAYA PENGUPASAN OVERBURDEN DAN ORE GETTING PADA BLOK ULUSAWA 3 DI PT. GERBANG MULTI SEJAHTERA

perencanaan biaya

Authors

  • Rizal Rindawuna Rizal Mahasiswa
  • Erwin Anshari Universitas Halu Oleo
  • WD Rizky Awaliah Nafiu Universitas Halu Oleo
  • Irfan Saputra Universitas Halu Oleo

Keywords:

cost planning, production costs, mining costs, Nickel Mining

Abstract

The process of mining activities carried out by PT. The Multi Prosperous Gate consists of land clearing and stripping overburden, ore getting, ore loading and transport. Therefore, to maximize mining activities, PT. Multi Prosperous Gate requires cost planning. The cost aspect in question is the cost of stripping overburden andore getting. This study aims to determine the number of loading and unloading equipment needed for stripping activities overburden andore getting, and determine the total cost required in stripping activities overburden andore getting. The number of digging equipment and hauling equipment can be calculated based on the productivity of heavy equipment and monthly production targets, in stripping activities overburden and ore getting using a loading excavator excavator Cat 320-Tier and excavator Sumitomo SH350, then for transportation overburden and ore getting using a means of transport Dump Truck Mercy-Axor 2528C. Based on the research results, it was found that the number of digging tools needed in the stripping activity overburden 1 unit and for activities loading overburden 1 unit as well as for hauling overburden by 1 unit. Then for activities ore getting from the first month to the second month as many as 3 units and on activities loading ore as many as 2 units as well as for hauling ore as many as 8 units. Then in the third month for activities or getting 2 units and for activities loading ore as much as 1 unit as well as for hauling ore in the third month as many as 4 units. Total cost for stripping activity overburden Rp.1.853.822.361 and for the total cost of activities or getting in the amount of Rp.15.527.625.972. so that the total cost required for mining activities in the Ulusawa Block 3 is  Rp.17.381.448.333.

References

Agung M., Wahab, dan Firdaus. 2020. Analisis Kebutuhan Alat Gali Muat Dan Angkut Pada Blok Ulin PT. Indra Bakti Mustika Kec. Langgikima Kab. Konawe Utara. Jurnal GeoMining. ISSN : 2774-2644:Vol. 1 Nomor 2: Hal. 79–88.

Dania, P., Sri W., dan Zaenal., 2018. Evaluasi Biaya Kepemilikan (Owning Cost) Dan Biaya Operasi (Operating Cost) Dump Truck Hino Ranger Ff 173 Ma Pada Penambangan Batu Andesit Di CV Panghegar, Blok Gunung Patapaan Desa Cilalaw , Kecamatan Sukatani, Kabupaten Purwakarta, Provinsi Jawa. Jurnal Teknik Pertambangan. ISSN : 2460-6599 : Vol. 4 Nomor 2 : Hal. 578–79.

Epi., Rr. Harminuke E., H., dan Abuamat H., 2017. Re Desain Pengaturan Peralatan Coal Getting Untuk Memenuhu Target Produksi Desember 2016. ISSN : 2549-1008 : Jp. Vol 1 Nomor 4: Hal. 28–37.

Febrianti, D., dan Zakia., 2019. Analisis Durasi Dan Perhitungan Biaya Penyusutan (Depresiasi) Alat Berat Excavator. Jurnal Teknik Sipil. ISSN : 2088-9321 : Vol. 8 Nomor 1: Hal. 10–19.

Hayati, N., dan M. Murad., 2020. Analisis Biaya Pemboran Inpit Drill Di Front X PT. ANTAM Tbk. Unit Bisnis Penambangan Nikel Sulawesi Tenggara. Jurnal Bina Tambang. ISSN : 2302-3333 : Vol. 5 Nomor 2: Hal. 88–98.

Hustrulid, W., Kuchta, M., dan R. Martin., 2013. Open Pit Mine Planning & Design 3rd Edition. CRC Press. ISBN-13: 978-1-4822-2117-6.

Istiqamah, D.,A., dan Mulya G., 2019. Kajian Teknis Optimasi Produksi Alat Gali Muat Dan Alat Angkut Pada Kegiatan Pengupasan Overburden Berdasarkan Efisiensi Biaya Operasional Di Pit Barat PT. Allied Indo Coal Jaya Kota Sawahlunto. Jurnal Bina Tambang. ISSN : 2303-3333 : Vol.5 Nomor 1 : Hal. 61–73.

Monika, I., 2017. Analisis Investasi Pengadaan Alat Berat Untuk Mencapai Target Produksi Batu Gamping 240.000 Ton/Tahun Dengan Metode NPV Dan IRR Di PT. Anugrah Halaban Sepakat.Jurnal Bina Tambang. ISSN: 2303-3333:Vol.3 Nomor 3: Hal.1014–2

Pujangga, A., dan Mulya G., 2021. Optimalisasi Produksi Alat Gali-Muat Dan Alat Angkut Pada Proses Pengupasan Overburden Untuk Mencapai Target Produksi per Bulan Pada Penambangan Batubara PT . Pengembangan Investasi Riau Coal Mine Project Desa Pematang Benteng Kecamatan Batang Peranap Kabupaten Indragiri Hulu Provinsi Riau. Jurnal Bina Tambang. ISSN : 2303-3333 : Vol. 6 Nomor 3: Hal. 143–58.

Putra, R.N., dan Kasim, T, 2019, Evaluasi Teknis Geometri Jalan Angkut Produksi Sebagai Upaya Percapaian Target Produksi Batubara 20000 ton/bulan di Tambang Terbuka PT. Allied Indo Coal Jaya (AICJ) Perambahan, Kecamatan Talawi, Kota Sawalunto, Sumatera Barat, Jurnal Bina Tambang, Vol.4, No.3, Hal: 77-88, ISSN: 2302-3333

Rostiyanti, S.F., 2008, Alat Berat Untuk Proyek Konstruksi, Jakarta: PT. Rineka Cipta.

Sandeir, E., dan Prabowo, H., 2018. Evaluasi Kebutuhan Dan Estimasi Biaya Alat Muat Kobelco 380 Dan Hitachi 350 Dengan Alat Angkut Scania P360 Dan Mercedez Actroz 4043 Pada Pengupasan Overburden PT. Caritas Energi Indonesia Jobsite KBB, Sarolangun.Jurnal Bina Tambang. ISSN : 2302-333 : Vol. 3 Nomor 3 : Hal. 1091–1100.

Sepriadi., dan Webisono K., 2017. Evaluasi Geometri Jalan Angkut Terhadap Produktifitas Overburden Di Pit Mt 4 Penambangan Air Laya Pt Bukit Asam (Persero), Tbk. Tanjung Enim Propinsi Sumatera Selatan.Jurnal teknik patra akademika. ISSN : 2621-9328 : Vol. 08 Nomor 02 : Hal. 1–9.

Sokop, R., M., Arsad. Tj., T., dan Malingkas G., 2018. Analisa Perhitungan Produktivitas Alat Berat Gali-Muat (Excavator) Dan Alat Angkut (Dump Truck) Pada Pekerjaan Pematangan Lahan Perumahan Residence Jordan Sea. Jurnal Tekno. ISSN : 0215-9617 : Vol. 16 Nomor 70: Hal. 83–88.

Vahlevi R., S., Widayati, dan Yuliadi., 2016. Owning Cost Dan Operating Cost Pada Penambangan Nikel Di PT Fajar Bhakti Lintas Nusantara Sub-KontraktorPT Sinar Karya Mustika Desa Elevanun , Kecamatan Pulau Gebe, Kabupaten Halmahera Tengah, Provinsi Maluku Utara. Prosiding Teknik Pertambangan. Vo. 2 Nomor 2 : ISSN 2460- 6499 : Hal. 431–39.

Wibisono, R., A., Yuliad., dan Marynto., 2018. Perancangan Pentahapan Kemajuan Tambang Batubara Dan Perencanaan Fleet Di PT Bukit Intan Indoperkasa , Desa Batang Kulur Kiri , Kecamatan Sungai Raya , Kabupaten Hulu Sungai Selatan , Provinsi Kalimantan Selatan. Design Sequence of Coal Mine and Planning O.Vol. 4 Nomor 1 : ISSN : 2460–6499): Hal. 352–61.

Winarso, W., 2014. Pengaruh Biaya Operasional Terhadap Profitabilitas (ROA) Pt Industri Telekomunikasi Indonesia (Persero). Jurnal Ecomedica. ISSN : 2355-0295 Vol. 2 Nomor 2 : Hal. 258–72.

Yastavia, R., dan Yulhendra D., 2020. Evaluasi Teknis Penambangan Bauksit Dari Front Penambangan Menuju Washing Plant Area Untuk Menganalisis Faktor Ketidaktercapaian Target Produksi Berdasarkan Efisiensi Biaya Operasional Penambangan PT . ANTAM Tbk . UBPB Tayan , Kalimantan Barat. Jurnal Bina Tambang. ISSN : 2302-3333 : Vol. 5 Nomor 1: Hal. 11–25.

Published

2023-07-06