PIT LIMIT DESIGN FOR NICKEL ORE MINING AT THE WANGGUDU PIT TAPUNOPAKA BLOCK PT ANTAM TBK NORTH KONAWE NICKEL MINING BUSINESS UNIT
Keywords:
Nickel Laterite, Pit Limit Design, Factor of SafetyAbstract
PT ANTAM Tbk UBPN North Konawe is a nickel mining company operating in North Konawe Regency, Indonesia. The company plans to develop a new open pit within the Tapunopaka block, requiring an optimized ultimate pit limit design to ensure slope stability, operational safety, and sustainable production. Geotechnical considerations play a critical role in determining the ultimate pit limit, as slope stability is strongly influenced by the physical and mechanical properties of the rock mass. The pit limit design process involved comprehensive geotechnical investigations, including laboratory testing and analysis of rock mass characteristics at the mining site. The ultimate pit limit for Pit Wanggudu was determined based on reserve block model evaluation and geotechnical analysis results. The selected slope geometry consists of a bench height of 6 m, a berm width of 2 m, and a batter angle of 65°, complemented by a two-lane haul road (ramp) with a total width of 9 m. This configuration was designed to maintain acceptable slope stability conditions in accordance with safety standards. Based on the pit limit design and the application of a company defined cut-off grade (COG) of 1.5% Ni, the total ore reserve is estimated at 470,796 tons. Assuming a mining recovery of 90%, the economically recoverable ore tonnage is approximately 423,716.4 tons. The average nickel (Ni) grade of the ore is 1.94%, which, after applying a dilution factor of 4%, results in a final average Ni grade of 1.86% and a stripping ratio (SR) of 2.3.
References
A. Sastra Pratama, M. Zam Mili, dan E. Anshari, “RANCANGAN PUSHBACK PENAMBANGAN NIKEL LATERIT PADA PIT 3 PT. ADHIKARA CIPTA MULIA KECAMATAN LASOLO KEPULAUAN KABUPATEN KONAWE UTARA PROVINSI SULAWESI TENGGARA,” Jurnal Riset Teknologi Pertambangan (J-Ristam, vol. 3, no. 2, 2023.
A. Waheed, Nickel Laterites Fundamentals of chemistry, mineralogy, weathering processes, formation, and exploration. Vale Inco, 2009.
J. Read dan P. Stacey, OPEN PIT SLOPE DESIGN. Collingwood: CSIRO, 2009.
N. Arif Wibawa, E. Anshari, I. Saputra, dan I. Sartika Ambarsari, “RANCANGAN PIT DAN SEQUENCE PENAMBANGAN BIJIH NIKEL PADA PIT B BLOK MANGROVE PT. INDRABAKTI MUSTIKA SITE LAMERURU,” Jurnal Riset Teknologi Pertambangan (J-Ristam, vol. 4, no. 1, 2024.
M. Yusuf Imana, Deniyatno, M. Ilham Kadar, dan “PERANCANGAN M. PIT Mustofa, DAN SEQUENCE PENAMBANGAN NIKEL PT ADHIKARA CIPTA MULIA DESA MAROMBO PANTAI KECAMATAN LASOLO KEPULAUAN KABUPATEN KONAWE UTARA PROVINSI SULAWESI TENGGARA,” Jurnal Riset Teknologi Pertambangan (J-Ristam, vol. 3, no. 2, hlm. 57–68, 2023.
Arif, Geoteknik Tambang. Jakarta: Gramedia Pustaka Utama, 2021.
D. C. Wyllie dan C. W. Mah, Rock Slope Engineering: Civil and Mining, 4th Edition, 4 ed. New York: Spon Press, 2005.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Noor Afandy, Erwin Anshari, Wira Yudha, Irfan Ido

This work is licensed under a Creative Commons Attribution 4.0 International License.