Pit Design and Mining Sequence of Laterite Nickel Ore in Block B7 of PT Koninis Fajar Mineral, Banggai Regency

Authors

  • Riyan Fansursyah
  • Erwin Anshari Halu Oleo University
  • Irfan Saputra Halu Oleo University
  • Asri Arifin Halu Oleo University

Keywords:

Nickel laterite, Pit Design, Mine Sequence

Abstract

Koninis Fajar Mineral Ltd. is a private company engaged in nickel mining, located in Banggai Regency with a WIUP area of 2.738 ha. The company has conducted exploration in block B7 and has met the criteria for reserve classification, thus requiring an efficient mining design to ensure smooth operations. This study aims to develop a pit design and mining sequence with safe slope geometry considerations to determine mineable reserves and mine life. Based on the research results, a pit design covering 8,97 ha was obtained, with parameters including a bottom pit and ramp width of 9 m, a maximum ramp gradient of 12%, and bench geometry derived from simulation and slope stability analysis categorized as safe. The obtained Factor of Safety (FK) meets the minimum requirements set by the Ministry of Energy and Mineral Resources Decree No. 1827 K/30/MEM/2018, namely a bench height of 6 m, bench width of 2 m, and slope angle of 55°. The pit design provides information on the amount of ore material that can be mined, totaling 392,906 WMT, and waste material of 576.312 WMT, resulting in a mining duration of 1,57 months. The pit design is divided into two stages: in the first sequence, pit opening covers 7,41 ha from an elevation of 266 to 242 masl, while in the second sequence, the pit expands to 8,97 ha mined from an elevation of 242 to 217 masl.

References

K. J. Agbelele, G. O. Adeoti, D. Y. Agossou, and G. G. Aisse, “Study of slope stability using the Bishop slice method: An approach combining analytical and numerical analyses,” Journal of Applied Sciences, vol. 13, no. 8, pp. 1446–1456, 2023, ISSN: 2165-3925.

M. Z. Arief, “Optimalisasi geometri lereng tunggal tambang nikel dengan kondisi statik dan dinamik,” Buletin Profesi Insinyur, vol. 7, no. 2, pp. 81–88, 2024, ISSN: 2654-5926.

I. Arif, Geoteknik Tambang: Mewujudkan Produksi Tambang yang Berkelanjutan dengan Menjaga Kestabilan Lereng. Jakarta: PT Gramedia Pustaka Utama, 2016, ISBN: 978-602-03-2735-8.

I. Arif, Nikel Indonesia. Jakarta: PT Gramedia Pustaka Utama, 2018, ISBN:978-602-06-1935-4

M. A. Azizi, R. Karim, I. Marwanza, D. Muhammad, and K. Ghifari, “Prediksi volume longsoran tambang terbuka nikel menggunakan metode kesetimbangan batas tiga dimensi,” Indonesian Mining Professionals Journal, vol. 1, no. 1, pp. 43–48, 2019, ISSN: 2714-8823.

Badan Standardisasi Nasional, SNI 1726:2019 tentang Tata Cara Perencanaan Ketahanan Gempa untuk Struktur Bangunan Gedung dan Non Gedung. Jakarta: BSN, 2019.

W. S. Bargawa, Perencanaan Tambang, 8th ed. Yogyakarta: Kilau Book, 2018, ISBN: 978-623-7594-31-4.

D. Ferdynan, S. Saptono, O. W. Lusantono, and D. W. Ratminah, “Application of technical implementation in nickel ore mining: Study case in nickel mining site at Indonesia,” IOP Conference Series: Earth and Environmental Science, vol. 1486, no. 1, p. 012033, 2025, ISSN: 1755-1307.

H. C. Hardiyatmo, Mekanika Tanah 2, 6th ed. Yogyakarta: Gadjah Mada University Press, 2018, ISBN: 978-602-386-312-9.

Hasria and S. Septiana, Geologi Endapan Nikel Laterit. Yogyakarta: CV Budi Utama, 2024, ISBN: 978-623-02-8371-0.

A. Hernadi, “Analisis spektrum respon gempa menggunakan peta gempa SNI 1726:2012 dan SNI 1726:2019 di Kota Tarakan,” Borneo Engineering: Jurnal Teknik Sipil, vol. 5, no. 3, pp. 335–347, 2021, E-ISSN: 2581-1134.

W. Hustrulid, M. Kuchta, and R. Martin, Open Pit Mine Planning and Design, 3rd ed. Leiden: CRC Press, 2013, ISBN: 978-1-4822-2117-6.

M. Y. Imana, M. I. Kadar, and M. Mustofa, “Perancangan pit dan sequence penambangan nikel pada Pit 4 PT Adhikara Cipta Mulia,” Jurnal Riset Teknologi Pertambangan (J-Ristam), vol. 3, no. 2, pp. 57–68, 2023, ISSN: 2621-3869.

Y. Indonesianto, Pemindahan Tanah Mekanis. Yogyakarta: CV Awan Poetih, 2016, ISBN: 978-602-820607-5.

A. Ito et al., “Geochemical constraints on the mobilization of Ni and critical metals in laterite deposits, Sulawesi, Indonesia: A mass-balance approach,” Resource Geology, vol. 71, no. 3, pp. 255–282, 2021, E-ISSN: 1751-3928.

Kementerian Energi dan Sumber Daya Mineral Republik Indonesia, Keputusan Menteri ESDM Nomor 1827 K/30/MEM/2018 tentang Pedoman Pelaksanaan Kaidah Teknik Pertambangan yang Baik. Jakarta: Kementerian ESDM, 2018.

B. A. Kennedy, Surface Mining, 2nd ed. Colorado: Society for Mining, Metallurgy, and Exploration Inc., 2009, ISBN: 978-0-87335-303-8.

Komite Cadangan Mineral Indonesia, Kode Pelaporan Hasil Eksplorasi, Sumber Daya Mineral, dan Cadangan Mineral Indonesia. Jakarta: PERHAPI–IAGI, 2017.

U. König, “Nickel laterites—Mineralogical monitoring for grade definition and process optimization,” Minerals, vol. 11, no. 11, p. 1178, 2021, ISSN: 0126-3463.

M. Wang, H. Li, and X. Jiang, “Stability analysis of high slopes in mines based on Slide and MIDAS,” SSRG International Journal of Civil Engineering, vol. 10, no. 6, pp. 86–94, 2023, ISSN: 2348-8352.

M. Nonsi, Y. I. Arifin, and N. Akase, “Analisis ketebalan endapan laterit dan pengaruhnya terhadap kadar nikel di daerah Koninis, Kabupaten Banggai,” UNM Geographic Journal, vol. 7, no. 2, pp. 48–56, 2024, E-ISSN: 2597-4076.

N. Payuyu, A. P. Permana, and R.

Hutagalung, “Analisis tipe batuan dasar pembentuk nikel laterit pada Block X Kabupaten Banggai,” J SIG (Jurnal Sains Informasi Geografi), vol. 5, no. 2, pp. 58–66, 2022, ISSN: 2621-3869.

A. S. Pratama, M. Deniyatno, M. Z. Mili, and E. Anshari, “Rancangan pushback penambangan nikel laterit pada Pit 3 PT Adhikara Cipta Mulia,” Jurnal Riset Teknologi Pertambangan (J-Ristam), vol. 3, no. 2, pp. 14–27, 2023, ISSN: 2621-3869.

R. Puspita, N. Ninasafitri, and M. R. Ente, “Characteristics of ultramafic rock and nickel laterite distribution in Siuna Area, Central Sulawesi,” Jurnal Geocelebes, vol. 6, no. 1, pp. 93–107, 2022, ISSN: 2579-5546.

E. Rusmana, A. Koswara, and T. O. Simandjuntak, Peta Geologi Lembar Luwuk, Skala 1:250.000, 1993.

W. L. Sarfin, E. Anshari, and W. R. A. Nafiu, “Rancangan sequence penambangan pada Blok A4 PT Adhi Kartiko Pratama,” Jurnal Locus Penelitian dan Pengabdian, vol. 2, no. 12, pp. 1163–1180, 2023, ISSN: 2829-7334.

S. Sukirman, Perencanaan Tebal Struktur Perkerasan Lentur. Bandung: Nova, 2010, ISBN: 978-602-96141-0-7.

A. Timchenko and J. L. Briaud, “Analysis of a database of open pit mine slope failures to predict travel distance, setback distance, and geometric properties,” Canadian Geotechnical Journal, vol. 60, no. 9, pp. 1315–1331, 2023, ISSN: 0008-3674.

D. C. Wyllie and C. W. Mah, Rock Slope Engineering: Civil and Mining Applications, 4th ed. London and New York: Spon Press, 2004, ISBN: 0-203-49908-5.

Published

2026-06-16